🏗️ Construction · Gantt
A typical schedule for building an independent house, from approvals and foundation to finishing and handover.
Drawing diagram…
Gantt chart for constructing a two-floor independent house over about 9 months: design and approvals (architectural drawings, plan sanction, soil test), foundation (excavation, footings, plinth), structure (ground floor slab, first floor slab, masonry), services (plumbing, electrical conduits in parallel), finishing (plastering, flooring, painting, fixtures) and handover (snag list, completion certificate).
gantt title House Construction (2 floors) dateFormat YYYY-MM-DD axisFormat %b section Design and approvals Architectural drawings :a1, 2026-10-01, 21d Plan sanction :a2, after a1, 30d Soil test :a3, 2026-10-10, 7d section Foundation Excavation :b1, after a2, 10d Footings and plinth :b2, after b1, 20d section Structure Ground floor slab :c1, after b2, 25d First floor slab :c2, after c1, 25d Masonry walls :c3, after c1, 40d section Services Plumbing :d1, after c2, 20d Electrical conduits :d2, after c2, 20d section Finishing Plastering :e1, after d1, 25d Flooring and tiling :e2, after e1, 20d Painting and fixtures :e3, after e2, 20d section Handover Snag list and fixes :f1, after e3, 7d Completion certificate :f2, after f1, 10d
How a building project moves through the local authority: plan approval, stage inspections during construction, and the occupancy certificate.
How a construction site orders materials: site request, quotes from suppliers, purchase order, delivery, quality check and payment.
A platform for running building projects: schedules, site diaries, drawings, RFIs, quality and safety checklists, and billing.
How building information modelling (BIM) data flows between designers, contractors and the owner: coordination, clash detection, quantities and handover.
A daily safety inspection routine on a construction site: checklists, hazard reporting, stop-work authority and follow-up.
Tables for a construction project system: projects, sites, work packages, subcontractors, materials, daily logs and payments.