🏗️ Construction · Gantt

House Construction Project Schedule

A typical schedule for building an independent house, from approvals and foundation to finishing and handover.

More Construction templates

Drawing diagram…

What this diagram shows

  • Approvals and soil testing come before any digging
  • Structure work follows floor by floor
  • Plumbing and electrical run in parallel with masonry

Prompt used

Gantt chart for constructing a two-floor independent house over about 9 months: design and approvals (architectural drawings, plan sanction, soil test), foundation (excavation, footings, plinth), structure (ground floor slab, first floor slab, masonry), services (plumbing, electrical conduits in parallel), finishing (plastering, flooring, painting, fixtures) and handover (snag list, completion certificate).

Mermaid code
gantt
  title House Construction (2 floors)
  dateFormat YYYY-MM-DD
  axisFormat %b
  section Design and approvals
  Architectural drawings   :a1, 2026-10-01, 21d
  Plan sanction            :a2, after a1, 30d
  Soil test                :a3, 2026-10-10, 7d
  section Foundation
  Excavation               :b1, after a2, 10d
  Footings and plinth      :b2, after b1, 20d
  section Structure
  Ground floor slab        :c1, after b2, 25d
  First floor slab         :c2, after c1, 25d
  Masonry walls            :c3, after c1, 40d
  section Services
  Plumbing                 :d1, after c2, 20d
  Electrical conduits      :d2, after c2, 20d
  section Finishing
  Plastering               :e1, after d1, 25d
  Flooring and tiling      :e2, after e1, 20d
  Painting and fixtures    :e3, after e2, 20d
  section Handover
  Snag list and fixes      :f1, after e3, 7d
  Completion certificate   :f2, after f1, 10d

Related templates

FlowchartConstruction

Building Permit and Stage Inspections

How a building project moves through the local authority: plan approval, stage inspections during construction, and the occupancy certificate.

SequenceConstruction

Construction Material Procurement

How a construction site orders materials: site request, quotes from suppliers, purchase order, delivery, quality check and payment.

C4 ArchitectureProConstruction

Construction Project Management Platform

A platform for running building projects: schedules, site diaries, drawings, RFIs, quality and safety checklists, and billing.

Data FlowConstruction

BIM Data Flow

How building information modelling (BIM) data flows between designers, contractors and the owner: coordination, clash detection, quantities and handover.

FlowchartConstruction

Construction Site Safety Inspection

A daily safety inspection routine on a construction site: checklists, hazard reporting, stop-work authority and follow-up.

Database ERDConstruction

Construction Project Database Schema

Tables for a construction project system: projects, sites, work packages, subcontractors, materials, daily logs and payments.